Purpose
Use the chsum command to change a job summary schedule.
See Also:
"Summary Commands" for related commandsPrerequisites
You must have the modify administrative domain's configuration right to run the chsum command.
Syntax
chsum::=
chsu•m [ --days/-d produce-days[,produce-days]... ] [ --reporttime/-t time ] [ --mailto/-m email-target[,email-target]... ] [ --addmailto/-a email-target[,email-target]... ] [ --rmmailto/-r email-target[,email-target]... ] [ [ --covers/-c duration ] | [ --since/-s "summary-start-day[ ]time" ] ] [ --backup/-B { yes | no } ] [ --restore/-R { yes | no } ] [ --orabackup/-b { yes | no } ] [ --orarestore/-e { yes | no } ] [ --scheduled/-S { yes | no } ] [ --user/-U { yes | no } ] [ --subjobs/-J { yes | no } ] [ --superseded/-D { yes | no } ] summary-name ...
Semantics
Refer to "mksum" for options not included in this section.
Adds additional email addresses to the job summary schedule.
Removes email addresses from the job summary schedule.
Specifies the name of the job summary schedule.
Example
ob> lssum
weekly_report Wed at 12:00
ob> chsum --addmailto jim@company.com --days Wed,Fri --reporttime 12:00
weekly_report
ob> lssu --long
weekly_report:
Produce on: Wed Fri at 12:00
Mail to: lance@company.com jim@company.com
In the report, include:
Backup jobs: yes
Restore jobs: yes
Scheduled jobs: yes
User jobs: yes
Subordinate jobs: yes
Superseded jobs: no